Waratah Private Hospital

30%

Cumulative Energy Reduction

$380,600

Cumulative Financial Savings

2,553

tCO2e Cumulative Emissions Avoided

“We engaged EP&T Global to help deliver on our sustainability objectives, delivering efficiency gains across the operation of our building’s mechanical plant and equipment. We have achieved great results to date, enhancing the buildings sustainability credentials while also passing on the benefits of lower energy costs to the hospital."

Jonathan Greenwood, Vice President - Portfolio Manager – AUS, Northwest Healthcare Properties Mgmt

Waratah Private Hospital is one of the most technologically advanced hospitals in Australia. It provides comprehensive healthcare in one building, with 7 state-of-the-art operating theatres, modern private en-suite patient rooms and full diagnostic, surgical and interventional facilities.

EP&T Global and Waratah Private have worked together in partnership since 2017, with the implementation of the EDGE Intelligent System. In that time EDGE has been the catalyst for on site energy savings initiatives such as:

  • CO (Carbon Monoxide) controls for carpark ventilation fans
  • LED upgrade and movement sensor control for carpark lighting
  • Modifying time schedules for AHUs serving theatres and other ancillary areas based on actual operational requirements
  • Ambient lockout strategy for boiler
  • Chiller water setpoint reset strategy
  • Chiller staging control